Storm sewer installation has progressed along Gilmer Road from Schwerman Road to south of Cardinal Drive and at the Gilmer Pond (next to Pond-A-Rudy).

The contractor is scheduled to begin storm sewer installation on Midlothian Road between Gilmer Road and Sylvan Drive this week, where the pipe has been delivered.

Additional roadway work will begin in the Spring, so disturbed areas are being covered with temporary erosion control blanket until work begins.

A temporary traffic signal at Gilmer Road & Midlothian Road is scheduled to be activated on Thursday 3/10/22.
This temporary signal will take the place of the existing traffic signal during construction, until the new permanent traffic signal is installed.

Please drive carefully through the construction zone.