There will be a New Traffic Pattern on Gilmer Rd starting Monday, 8/29/22, weather dependent. Traffic will be split with EB Gilmer Rd on the new pavement and WB Gilmer Rd remaining on the existing pavement. The construction will proceed in the middle between opposing lanes of traffic. During this time, vehicles will not be able to cross through the work zone in the middle. Access from side streets and driveways on Gilmer Rd will be right-in/right-out only. This stage is estimated to last about 4 weeks.
There will be no change on Midlothian Rd.
August 25, 2022